Throughout September there will be some planned high voltage cable installations taking place between the new Energy Centre in Tudor Grange Park and Station Road by John Lewis as part of the Solihull Town Centre Low Carbon Energy Network.
The works will be carried out as part of a phased programme to mitigate any impact on the town centre.
These works will start on the 1st of September, and the expected duration is up to 3 weeks, starting at Blossom Field Road.
We will ensure that entrances and exits remain open to private dwellings, offices and businesses as the works are completed, and the majority of the works will be limited to between the hours of 07:30 and 17:00.
High voltage cable installations taking place on Blossomfield Road from the entrance of Tudor Grange Leisure centre car park up to the pedestrian crossing between Station Approach and Homer Road.
Traffic flow will be maintained in both directions, and a pedestrian diversion will be in place as per the traffic management plan.